What is scope creep?

Prepare for the FITSI Manager Exam with our comprehensive quiz. Access flashcards and multiple choice questions, each with hints and explanations. Ensure success on your exam day!

Multiple Choice

What is scope creep?

Explanation:
Scope creep refers to the phenomenon where a project's scope expands beyond its original boundaries without the corresponding adjustments in resources, timelines, or budgets. It typically occurs when new features or requirements are added without formal approval and can lead to increased costs, extended timelines, and potential project failure if not managed effectively. The correct choice emphasizes that these changes are "uncontrolled," highlighting that scope creep often happens gradually and without clear definition or approval processes. This unintended expansion can disrupt project management and lead to resource strain as teams attempt to accommodate these new demands. Recognizing and addressing scope creep is crucial for maintaining project integrity and ensuring that objectives are met within the original parameters.

Scope creep refers to the phenomenon where a project's scope expands beyond its original boundaries without the corresponding adjustments in resources, timelines, or budgets. It typically occurs when new features or requirements are added without formal approval and can lead to increased costs, extended timelines, and potential project failure if not managed effectively.

The correct choice emphasizes that these changes are "uncontrolled," highlighting that scope creep often happens gradually and without clear definition or approval processes. This unintended expansion can disrupt project management and lead to resource strain as teams attempt to accommodate these new demands. Recognizing and addressing scope creep is crucial for maintaining project integrity and ensuring that objectives are met within the original parameters.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy